Now and Then
The aerials shown to the right will show the progress from the original location to the updated changes.


This project extends from roughly the intersection with West Main Street and the intersection with Court Lane.
Significant Drainage improvements, road widening and re-building, road re-surfacing, new sewer line and structures, enhanced storm water management, curb and gutter and sidewalk on the south side from the traffic light to the lower hospital entrance, conduits and vaults for decorative ground-mount street lighting, intersection improvements, pedestrian improvements, coordination with the hospital campus walking trail (to be built).
The aerials shown to the right will show the progress from the original location to the updated changes.
Memorial Drive Public Budget 09 26 2022
Budget (changes):
Construction (CN) Contract with GEI - $1,869,656.66
Effective Date: 02/25/2023
Find information here for Maintenance of Traffic Maps.
Walk-Through Inspection & Punch-List - March 14, 2023
Temporary/Final End of Detour - March 17, 2023
Estimated Re-Open to Two-Way Traffic - March 17, 2023
Surface Paving Commences - April 3, 2023
(under one-lane, one-way flagging operations or re-opening detour for a few days)
Pavement Marking - April 10, 2023
(under one lane, one-way flagging operations or re-opening the detour for a few days)
Construction Complete - April 14, 2023
E&S Review/Inspection - April 19-26, 2023
Final Inspection - May 3, 2023
Project Acceptance - May 4, 2023
Contract Completion - May 5, 2023