CURRENT SCHEDULE - Memorial Drive Corridor Improvements

Start Date:
September 27, 2022
End Date:

CURRENT SCHEDULE

Memorial Drive Corridor Improvements

UPC; 112940

Version: September 27, 2022

ITB/RFP - March 25, 2022

Bids Due - May 5, 2022

Council Selection & Authorization - May 9, 2022

Notice of Award - May 10, 2022

General Excavation, Inc.

Contract Date - August 19, 2022

Pre-Construction Conference - August 25, 2022

Notice to Proceed (NTP) - September 6, 2022

Start of Project Activities - September 9, 2022

Work Zone Signs Installation - September 12, 2022

Maintenance of Traffic – Phase I - September 19, 2022

MOT Change – Phases II/III - December 13, 2022

Surface Paving Commences - May 12, 2023

Walk-Through Inspection & Punchlist - May 23, 2023

Construction Complete - June 14, 2023

Final Inspection - June 14, 2023

Project Acceptance - June 15, 2023

Detour Lifted - June 15, 2023