CURRENT BUDGET - Memorial Drive Corridor Improvements

Start Date:
September 27, 2022
End Date:

CURRENT BUDGET

Memorial Drive Corridor Improvements

UPC: 112940

Version: September 27, 2022

Overall Project Funding Available: $2,658,000

VDOT Revenue Sharing – 50/50 Match Monies

VDOT Overall Available Share: $1,329,000

Local Overall Available Share: $1,329,000

Project Estimating – VDOT PCES (April 7, 2022): $2,631,777

Preliminary Engineering (PE): $121,771

Construction (CN): $2,408,747

Right-of-Way & Utilities (RW): $101,859

----------------------------------------------------------------------

Construction (CN) Contract with General Excavation, Inc.: $1,568,358