The Town of Luray Public Works and Police Departments wish to
notify you of Utility & Street Construction in the following location:
East Main Street
(between Broad Street and the RR Tracks)
This segment is planned for excavation, asphalt patching
and concrete replacement work from
Monday, March 18 up to Friday, May 10, 2024
(weather-permitting).
Work will primarily be conducted in the parking lane,
gutter pan and sidewalk edges. The entrance to the
Town office parking lot will be replaced.
Plans and specifications for the project are available
for review at the Town office.
PLEASE BE ALERT FOR THE SHORT-TERM PARKING LANE CLOSURES AND
TRAFFIC INTERUPTIONS THAT WILL AFFECT DRIVING/WALKING IN
THESE SECTORS. INTERMITTENT FLAGGING OPERATIONS MAY OCCUR.
The Contractor, Chris Judd, will be working with individual businesses to reduce
parking and pedestrian access impacts as much as possible during this project.
Loose gravel and uneven pavement/concrete will be present during the work.
Dust, noise, short traffic delays, and altered travel-ways will likely OCCUR.
We apologize in advance for any inconvenience.
Phone: 540.743.5511 • Fax: 540.743.1486 • www.townofluray.com